AKRON, Ohio, March 2, 2026 /PRNewswire/ -- FirstEnergy Transmission LLC (FET) has been selected by regional transmission grid operator PJM Interconnection LLC to build several important projects that ...
While other grid operators are set to follow suit this year, the Midcontinent and New York grid operators don't plan to adopt the more precise line ratings until 2028.
FirstEnergy (NYSE:FE) has been selected by PJM Interconnection to lead several major power grid modernization projects in Ohio and Pennsylvania. The projects involve substantial investment in ...
RICHMOND, Va.--(BUSINESS WIRE)--Regional grid operator PJM Interconnection has selected several electric transmission projects that will be jointly developed by Dominion Energy, American Electric ...
The project will enhance electric reliability and affordability for West Virginia, Pennsylvania and the MidAtlantic region.
The average cost of wholesale power in PJM is less than what Lazard reports is the cost of building and operating new electricity generation.
FERC ordered PJM to create new transmission service options for large co-located loads and to clarify interconnection rules. The order attempts to balance speed to power and reliable service for large ...
Add Yahoo as a preferred source to see more of our stories on Google. Solar panels are seen on Aug. 20, 2015, at the Southern Maryland Electric Cooperative's 5.5-MW solar farm in Hughsville, Maryland.
FirstEnergy Transmission will invest about $950 million to modernize equipment, rebuild older lines and upgrade substations.